March 23–29, 2026

1 meeting · 20 minutes of video

The Southborough School Committee met to review and approve an informational flyer regarding the proposed Trottier Middle School roof project. The flyer explains that voters at the April 11 Annual Town Meeting must authorize the total estimated gross cost of $8,833,964 to meet state guidelines. State grant reimbursements are projected to cover 41.52 percent of the project, lowering the net cost to taxpayers to approximately $5.38 million. The committee approved the flyer for distribution through school channels, municipal buildings, and local media.

What mattered this week

Dates mentioned

  • April 11: Annual Town Meeting vote on Trottier roof project (past)

Everything coming up

Southborough School Committee

Tuesday, March 24, 2026, 20 min recording. Watch the full meeting · All School Committee meetings

The School Committee approved an informational flyer explaining the proposed $8.8 million Trottier roof project ahead of Town Meeting.

Full summary 1 topic · 1 vote

The Southborough School Committee held a brief special meeting to review an informational flyer for the Trottier Middle School roof project. Members adjusted wording to clarify that state rules require Town Meeting to authorize the full $8.8 million gross cost even though state grant reimbursements will lower the net town cost to roughly $5.38 million. The committee approved the revised flyer for distribution across school and municipal channels ahead of the April 11 Annual Town Meeting.

  • Trottier Middle School roof project informational flyer

    Schools. Watch at 1:45 Trottier Middle School roof replacement · 2 meetings

    The committee reviewed and revised a draft informational flyer to inform voters about the condition of the Trottier Middle School roof and the upcoming funding request. Members emphasized clearly distinguishing between the total gross appropriation required by the Massachusetts School Building Authority and the town's net cost after grant reimbursement.

    • The project is scheduled for votes at the April 11 Annual Town Meeting and on the town election ballot.
    • Total estimated project cost is $8,833,964, with an estimated MSBA reimbursement of 41.52% ($3,456,367).
    • The estimated net cost to Southborough taxpayers is $5,377,597.
    • Members adjusted the flyer to clarify that voters must authorize the gross amount of approximately $8.8 million, simplify cost line items, and add a link to full project reports.
    • Plans for distributing the flyer include ParentSquare, elementary school student backpacks, town news sites, Town Hall, the library, and the Senior Center.

    Outcome: Flyer approved as edited

    Why it matters: Residents will vote at Town Meeting and the town election on whether to authorize borrowing for the multi-million dollar school roof replacement.

Votes

MotionResultTime
Approve the one-page flyer for the Trottier Middle School roof project as edited Passed, 4-0 18:55

Next steps and dates mentioned

  • April 11: Annual Town Meeting vote on Trottier roof project

Note on the recording: One committee member experienced remote connection issues during the discussion and was disconnected during the roll call vote.