Where it stands as of Thu, Oct 8
The Zoning Board of Appeals unanimously approved the Chapter 40B comprehensive permit for the proposed 32-unit rental townhouse development in May 2026. The project remains before the Conservation Commission, which continued its Notice of Intent hearing on October 8 pending a peer review report from Lucas Environmental. Site wastewater plans also advanced in September when the Board of Health approved a septic variance for the property.
- For Zoning Board of Appeals Voted unanimously on May 6, 2026, to approve the comprehensive permit conditions and waivers for the 32-unit townhouse project.
- Undecided Conservation Commission Continued the Notice of Intent hearing on Oct 8, 2026, while awaiting a completed peer review from Lucas Environmental.
- For Board of Health Voted 2-1 on Sep 15, 2026, to grant a 6-foot foundation setback variance for a septic pump chamber on the property.
- For Planning Board Voted 5-0 on June 22, 2026, to recommend a 90-day extension of the temporary certificate of occupancy for the site's storage facility.
Votes
| Date | Board | Motion | Result | Video |
|---|---|---|---|---|
| Conservation Commission | Continue the Notice of Intent hearing for 250 Turnpike Road and 0 Parkerville Road 250 Turnpike Road 40B development | Passed4-0 | 21:57 | |
| Conservation Commission | Continue the public hearing for 250 Turnpike Road to the next meeting on October 8, 2026. 250 Turnpike Road 40B development | Passed5-0 | 1:18:40 | |
| Board of Health | Authorize the Health Department health agents and sanitary inspector to sign the variance for 250 Turnpike Road on behalf of the Board of Health. 250 Turnpike Road 40B development | Passedunanimous | 56:07 | |
| Board of Health | Grant a 6-foot foundation setback variance for the pump chamber at 250 Turnpike Road. 250 Turnpike Road 40B development | Passed2-1 | 55:33 | |
| Conservation Commission | Continue the public hearing for 250 Turnpike Road and 0 Parkerville Road to September 17, 2024 250 Turnpike Road 40B development | Passed5-0 | 23:48 | |
| Conservation Commission | Continue the public hearing for 250 Turnpike Road to the next meeting 250 Turnpike Road 40B development | Passed5-0 | 1:13:34 | |
| Planning Board | Recommend to the building commissioner to extend the temporary certificate of occupancy for 250 Turnpike Road for 90 days from the date of expiry 250 Turnpike Road 40B development | Passed5-0 | 1:00:58 | |
| Conservation Commission | Continue the public hearing for 250 Turnpike Road and 0 Parkerville Road to June 25, 2026. 250 Turnpike Road 40B development | Continued4-0 | 49:07 | |
| Zoning Board of Appeals | Motion to accept and approve the comprehensive permit conditions and waivers for 250 Turnpike Road as revised. 250 Turnpike Road 40B development | Passedunanimous | 1:49:55 |
Every time it came up newest first
-
Notice of Intent: 250 Turnpike Road and 0 Parkerville Road
The commission took up a continued hearing for a proposed 32-unit rental townhouse development at 250 Turnpike Road and 0 Parkerville Road. The conservation agent confirmed that peer reviewer Lucas Environmental is still completing their review, necessitating a continuance.
- Project involves 32 rental townhouse units.
- Locations are 250 Turnpike Road and 0 Parkerville Road.
- Lucas Environmental peer review is expected prior to the next session.
Outcome: Continued
-
Continued hearings: 250 Turnpike Road and 0 Southville Road
The commission formally opened and continued two public hearings at the request of the applicants without receiving testimony.
- 250 Turnpike Road and 0 Parkerville Road involves a Notice of Intent for the construction of 32 townhomes.
- 0 Southville Road involves a Notice of Intent and Stormwater Management Permit for two apartment buildings.
Outcome: Both hearings were continued to October 8, 2026.
-
Septic pump chamber variance for 250 Turnpike Road
Engineer James Tetreault presented a plan for 250 Turnpike Road to replace a failing, deteriorated sewer pipe hung under a footbridge with a new pump chamber and force main. Because of site constraints and a required 25-foot wetland setback, the applicant requested a variance from the standard 10-foot building foundation setback to place the pump chamber 6 feet from the building wall. The board approved the 6-foot variance with a vapor barrier condition, while noting that the broader replacement plan and leaching area must still be reviewed with DEP and the Conservation Commission.
- Property is located at 250 Turnpike Road, also known as the Beehive building.
- Applicant requested a 6-foot setback from the building foundation instead of the standard 10 feet under Title 5.
- A 40-mil impermeable vapor barrier will be installed along the building foundation to prevent any gas migration.
- The project will require a temporary crossing and Notice of Intent approval from the Conservation Commission.
- The board separately authorized department health agents and the sanitary inspector to sign the variance paperwork.
Outcome: Variance approved 2-1 (Liz Zadek voting against). Signing authorization passed 3-0.
-
250 Turnpike Road townhome development continuance
The commission opened a continued public hearing for a notice of intent to construct 32 rental townhomes at 250 Turnpike Road and 0 Parkerville Road. The applicant requested a continuance because peer review funds were recently received and the technical review is just getting underway.
- Address: 250 Turnpike Road and 0 Parkerville Road (Map 27, Lots 46 and 2A)
- Proposal entails 32 rental townhomes
- Peer review has just started
Outcome: Hearing continued to September 17, 2024.
-
Continued Notice of Intent: 250 Turnpike Road townhomes
The applicant for a 32-unit townhome development provided a brief procedural update. The applicant plans to submit a revised filing covering the replication area, and peer review will begin once review fees are settled.
- Location: 250 Turnpike Road and 0 Parkerville Road.
- Proposal entails 32 townhomes.
- Revised submission anticipated by the end of June to prepare for peer review.
Outcome: Hearing continued to July 23, 2024.
-
250 Turnpike Road temporary occupancy extension
Representative Georgeconn Banan of FD 250 Turnpike LLC requested a 90-day extension of the temporary certificate of occupancy for the Beehive Storage facility. Banan explained that because the access bridge over the wetlands has deteriorated, the applicant plans to install a dedicated septic system on the upper lot for the storage building and a separate system on the lower lot for the future contractor bays, rather than connecting across the bridge. The board voted to recommend that the building commissioner grant a 90-day extension.
- Location: 250 Turnpike Road (Beehive Storage and contractor yard)
- Current temporary certificate of occupancy recently expired
- Applicant planning soil percolation testing with the Board of Health for separate upper-lot septic
- Applicant plans future Approval Not Required (ANR) lot division and site plan modification
Outcome: Voted to recommend a 90-day extension of the temporary certificate of occupancy
-
NOI: 250 Turnpike Road 32-unit 40B townhouse development
Expedited Engineering presented a Notice of Intent on behalf of FD 250 Turnpike LLC for a Chapter 40B comprehensive permit project consisting of 32 townhouse-style rental units. Approximately 3.5 acres of the 5.2-acre parcel will be altered, involving work within the 100-foot buffer zone and the local 20-foot no-disturb zone. Discussion centered on wildlife passage for salamanders near an onsite vernal pool, waiver of local town bylaws under Chapter 40B, and proposed native buffer plantings.
- Address: 250 Turnpike Road and 0 Parkerville Road, Map 27, Lots 46 and 2A.
- Proposal includes 32 rental townhomes, with eight units designated affordable, allowing all 32 to count toward the town housing inventory.
- Plans incorporate a 4-foot-wide by 2-foot-high critter culvert under the roadway for amphibian migration between wetland areas.
- Local wetlands and stormwater bylaws were waived by the Zoning Board of Appeals under Chapter 40B, but state Wetlands Protection Act requirements still apply.
- Awaiting formal peer review from Lucas Environmental and town counsel advice regarding whether waivers cover access parcel Lot 2A.
Outcome: Hearing continued to June 25, 2026.
-
250 Turnpike Road 40B comprehensive permit decision
Town special counsel presented the detailed draft comprehensive permit decision, findings of fact, conditions, and waivers for a Chapter 40B development at 250 Turnpike Road and 9 Parkerville Road. The proposed development consists of 32 rental townhouse units, including eight affordable units (25 percent) restricted to households earning up to 80 percent of area median income. The board reviewed dozens of specific conditions covering pre-construction reviews, peer engineering oversight, wetland buffer zone mitigation, traffic and school bus accommodations, stormwater management, and dual regulatory agreements to protect long-term affordability.
- Location: 250 Turnpike Road and 9 Parkerville Road (approximately 3.5 acres)
- Project scope: 32 rental townhouse units (24 two-bedroom and 8 three-bedroom units), with 8 designated affordable units
- Condition 11 amended to clarify that final site plans will depict 6-foot privacy fencing on the project property rather than tying it to abutter agreements
- Condition 73 adjusted to specify that no building permits for vertical construction will be issued prior to wastewater approvals
- Includes a requirement for a springing local regulatory agreement to maintain affordability in perpetuity after state monitoring ends
Outcome: The board voted unanimously to approve the comprehensive permit conditions as revised.
-
250 Turnpike Road 40B application status
Town staff updated the commission on the comprehensive permit application for 250 Turnpike Road. The Zoning Board of Appeals closed its public hearing on April 15 and is set to deliberate on a draft decision on May 6, with a statutory filing deadline of May 25. The draft decision incorporates various conservation-related conditions, including invasive species management, wildlife passage grates, fencing, and buffer zone plantings.
- ZBA closed the public hearing on April 15, 2026.
- ZBA deliberation on draft decision scheduled for May 6, 2026; filing deadline is May 25, 2026.
- Key conservation conditions include an invasive species management plan, grates on the wildlife tunnel, buffer zone plantings, and nesting boxes.
Outcome: Discussion only; no commission vote taken.