School officials reported that bids for the Neary Elementary School roof replacement totaled roughly $2.8 million, well below the $4.5 million appropriation, with construction beginning in late June. The district also executed a $165,000 feasibility study contract with Tappé Architects to evaluate elementary facility options ahead of a potential fall Special Town Meeting. Meanwhile, the Community Preservation Committee reviewed Fall Town Meeting project proposals, including an estimated $900,000 golf course irrigation project and Fay Memorial Park upgrades. Additionally, the Board of Health examined asphalt plant odor mitigation efforts, and the Zoning Board of Appeals granted setback relief for a Turnpike Road home subject to Board of Health septic review.

What mattered this week

Dates mentioned

  • Friday, June 12, 2026: Pre-construction meeting with general contractor and subcontractors for Neary roof replacement (Southborough School Committee) (past)
  • June 13, 2026, at 8:00 AM: Trail construction and maintenance work party off Boston Road (Trails Committee) (past)
  • June 16, 2024 at 6:45 PM: Joint meeting with the Select Board to appoint a trustee to fill the library board vacancy (Library Board of Trustees) (past)
  • June 30, 2026: Deadline for Community Preservation Act Phase 2 grant application (Trails Committee) (past)
  • June 30, 2026: Deadline for revised applications for Fall Special Town Meeting CPA articles (Community Preservation Committee) (past)
  • July 7, 2026 at 11:00 AM: Public hearing on draft revisions to septic and private well regulations (Board of Health) (past)
  • July 15, 2026: Public hearings on two variances and a special permit for Costco lighting and retaining walls (Zoning Board of Appeals) (past)

Everything coming up

Key meetings

Southborough School Committee

Wednesday, June 10, 2026, 1 hr 12 min recording. Watch the full meeting · All School Committee meetings

School Committee reviews favorable $2.8 million Neary roof bids, a $165,000 feasibility contract for school building options, and staff laptop leasing.

Full summary 10 topics · 4 votes

The Southborough School Committee recognized ten retiring district staff members and received end-of-year school updates from principals. Officials reported that bids for the Neary Elementary School roof replacement came in at roughly $2.8 million, substantially below the $4.5 million appropriation, with construction beginning in late June. The committee also discussed a newly executed $165,000 feasibility study contract with Tappé Architects for elementary facilities planning, reviewed a proposed four-year lease for staff MacBooks, and approved year-end budget transfers.

  • Recognition of district retirees

    Schools. Watch at 0:21

    The superintendent and committee recognized ten retiring district educators and support professionals, representing over 200 collective years of service to Southborough public schools. Honorees included Finn School Principal Clayton Ryan and Neary Elementary Principal Kathleen Valenti, along with several longtime classroom teachers and educational support personnel.

    • Finn School Principal Clayton Ryan retired after serving the district since 1999 and as school administrator since 2012.
    • Neary Elementary School Principal Kathleen Valenti retired after leading the school since 2014.
    • Other recognized retirees included teachers Julie Perrault and Katrina Foley, tutor Jody Baum, and educational support professionals Lori Caccavaro, Diana Posk, Kathleen Riley, Maureen Sullivan-Alves, and Lorraine Muench.
    • The committee recessed briefly to celebrate with the retirees.

    Outcome: Informational recognition; no formal action taken.

  • Principals end-of-year reports

    Schools. Watch at 14:48

    Principals from Finn, Woodward, Neary, and Trottier schools presented highlights from end-of-year activities across the district. Highlights included the annual Algonquin Senior Stroll visiting elementary classrooms, expanding school therapy dog programs, spring concerts, middle school fine arts events, and student STEM initiatives.

    • Finn School held its Grade 1 concert and celebrated over a dozen community seniors who volunteer regularly in classrooms.
    • Woodward School welcomed Archie, a trained therapy dog partnered with a staff member, and hosted a Memorial Day concert with Southborough veterans.
    • Neary School engaged 196 students across bands, chorus, and orchestra, and hosted a fourth-grade STEM unit with the U.S. Army Natick Soldier Center.
    • Trottier Middle School held Greek and Roman Day, recorded its Big Band at WICN in Worcester, and hosted a multicultural fair representing 34 international flags.

    Outcome: Reports received.

  • Elementary School Building Committee update

    Schools. Watch at 35:40 Neary School building project · 16 meetings

    The chair of the Elementary School Building Committee reported that a $165,000 contract with Tappé Architects was officially executed to lead the feasibility study and schematic design phase for elementary school facilities. School Committee members stressed the need to adhere to tight timelines to present options to voters at a potential fall Special Town Meeting and emphasized keeping district administration actively involved in committee meetings.

    • A $165,000 feasibility and schematic design contract with Tappé Architects was executed on June 10.
    • The building committee plans to schedule its initial working meetings with Tappé Architects within the next one to two weeks.
    • Committee members discussed targeting the fall Special Town Meeting to present building options to the town.
    • School Committee member Roger Challen raised concern over district administration attendance at recent building committee sessions and urged tight coordination.
    • School Committee Chair Chelsea Malinowski noted that the Select Board must soon establish the fall Town Meeting date to avoid scheduling conflicts.

    Outcome: Update accepted; initial meetings with architects planned for mid-to-late June.

    Why it matters: The feasibility study evaluates future elementary school construction and renovation options that will ultimately go before town voters for major capital funding.

  • Staff technology four-year lease proposal

    Schools. Watch at 48:50

    The superintendent presented a plan recommended by the technology director to enter a four-year lease for approximately 103 to 105 staff Apple MacBooks. The district's current teacher laptops are six to eight years old and were purchased refurbished, leading to mounting maintenance issues.

    • The proposal covers 103 to 105 new Apple laptops for teachers and professional staff.
    • The lease costs roughly $20,000 annually over four years, fitting within the district's existing $25,000 annual technology line item without increasing the budget.
    • The agreement includes four years of technical support, device management, and warranty coverage.
    • At lease end, the district can buy out the devices for $1 each or use Apple's trade-in buyback program.
    • Older devices that remain functional will be redeployed to support personnel and students.

    Outcome: Discussion only; proposed lease will be funded through already approved operating funds.

    Why it matters: Ensures school faculty have functional modern technology while establishing a predictable four-year replacement cycle within existing taxpayer-funded operating budgets.

  • Neary School roof project update

    Schools. Watch at 54:14 Neary School roof replacement · 4 meetings

    The assistant superintendent presented results from the competitive bidding process for the Neary Elementary School roof replacement. Combined low bids totaled approximately $2.8 million, well below the $4.5 million appropriation approved at Town Meeting, with construction slated to begin in late June.

    • Total low bids for general contracting and filed sub-bids (plumbing, HVAC, and electrical) totaled approximately $2.8 million.
    • Voters previously authorized borrowing of up to $4.5 million for the project.
    • A pre-construction meeting with the general contractor, subcontractors, and school administration is scheduled for Friday morning.
    • Work is targeted to begin in late June, with 85% to 90% completion anticipated before school opens in late August.
    • The district plans informational updates to incoming fourth- and fifth-grade families in mid-July and around August 1.

    Outcome: Project moving into construction late June; contract includes a change order contingency reserve.

    Why it matters: A major capital roofing project is proceeding nearly $1.7 million under its authorized appropriation while minimizing disruption to returning elementary students.

  • Relocation of Summer Extended Day Program

    Schools. Watch at 59:22 Neary School roof replacement · 4 meetings

    Due to construction on the Neary Elementary roof over the summer, the Southborough Extended Day Program (SEDP) summer program is relocating to Finn Elementary School. Administration noted that adjustments have been made to accommodate older children and all enrolled families have been informed.

    • SEDP Summer Fun program relocated from Neary School to Finn School for the summer.
    • Programming begins after the July 4 holiday.

    Outcome: Relocation finalized.

  • FY26 budget transfers and year-end financial report

    Schools. Watch at 1:01:43

    The director of finance and operations presented the May 31 general fund budget report showing district expenditures of just over $19 million and encumbrances of $5.29 million, leaving a balance of $147,000 (0.59% of the operational budget). The committee approved line-item budget transfers to cover over-expended function codes in administrative technology, athletics, and custodial salaries driven by substitute staffing, utilities, and collaborative tuition pressures.

    • District had an available balance of $147,000 as of May 31.
    • Available balance dropped by $74,000 from the prior month due to year-end substitute staffing, utilities, and collaborative tuition costs.
    • Budget transfers were required to rebalance overages in Administrative Technology, Athletics, and Custodial Salaries.

    Outcome: The committee voted 5-0 to approve the FY26 line-item transfers and accept the monthly General Fund report until audited.

  • Revolving accounts update

    Schools. Watch at 1:04:26

    Finance staff presented projected year-end fund balances across the district's revolving accounts, noting that all four programs remain financially stable. Staff also explained that the preschool revolving account will split from the Northborough-Southborough regional account into independent town accounts starting in the upcoming fiscal year.

    • Projected year-end balances include Food Services at $112,000, Facility Rentals at $23,000, Extended Day at $563,000, and Preschool at $102,000.
    • Facility rental revenues will be replenished next fiscal year by leases from Assabet Valley Collaborative, Northborough, and the regional district.
    • An estimated $85,000 spent prior to town meeting approval could not be charged back to the facility revolving fund.
    • Northborough and Southborough preschool revolving funds are officially separating for the upcoming school year.

    Outcome: Report accepted.

Routine business (2 items)
  • Superintendent enrollment report

    Schools. Watch at 1:00:14

    Superintendent Martineau reviewed current enrollment projections, clarifying that Finn School will run seven sections of kindergarten and seven sections of first grade next school year. The district is currently in the process of hiring a kindergarten teacher and fourth-grade teacher.

    • Finn School will have seven sections of kindergarten and seven sections of grade one.
    • Postings for open elementary teaching roles are underway with strong candidate pools.

    Outcome: Report received.

  • Routine business

    Schools. Watch at 1:03:39

    The committee reviewed routine administrative items including May warrants and payrolls, the personnel report, open meeting minutes, and the public release of past executive session minutes before entering executive session.

    • Approved accounts payable warrants and two payroll runs for the month of May.
    • Personnel report noted appointments, retirements, and the resignation of a Woodward art teacher.
    • Approved open meeting minutes from May 13, 2026.
    • Approved the public release of executive session minutes from September 17, 2024; August 7, 2025; September 10, 2025; October 8, 2025; and November 12, 2025.
    • Voted by roll call to enter executive session regarding collective bargaining strategy and security personnel/devices, not to reconvene in open session.

    Outcome: All routine motions approved unanimously.

Votes

MotionResultTime
Vote to accept the FY26 monthly General Fund report as of May 31, 2026 until audited and approve the overexpended function codes listed. Passed, 5-0 1:03:36
Vote to approve warrants and payrolls as presented in the packet. Passed, 5-0 1:04:23
Vote to release executive session minutes from September 17, 2024; August 7, 2025; September 10, 2025; October 8, 2025; and November 12, 2025. Passed, 5-0 1:10:41
Vote to enter executive session under M.G.L. c. 30A, Section 21(a)(3) to discuss strategy regarding collective bargaining with Southborough Teachers Association Unit C (administrative assistants and educational support professionals), and Section 21(a)(4) to discuss security personnel, devices, or strategies, not to reconvene in open session. Passed, 5-0 1:12:00

Next steps and dates mentioned

  • Friday, June 12, 2026: Pre-construction meeting with general contractor and subcontractors for Neary roof replacement
  • Mid-to-late June 2026: Elementary School Building Committee initial working meeting with Tappé Architects
  • Mid-July and August 1, 2026: Informational communications to incoming Neary fourth- and fifth-grade families regarding roof construction
  • Late August 2026: Substantial completion target (85-90%) for Neary roof replacement

Board of Health

Tuesday, June 9, 2026, 31 min recording. Watch the full meeting · All Board of Health meetings

The Board of Health reviewed asphalt plant odor complaints, updated body art regulations, and authorized constable service for an unlicensed business.

Full summary 7 topics · 4 votes

Following an executive session, the Board of Health approved an employment contract renewal for the town sanitary inspector. The board received a report on an inter-agency meeting regarding ongoing odor issues from the Brox asphalt plant and reviewed state environmental findings. Members also authorized constable delivery of a cease-and-desist order to an unlicensed body art establishment on Turnpike Road, adopted revised body art regulations, and completed the annual performance evaluation and salary adjustment for the public health director.

  • Brox asphalt plant odor and mitigation follow-up

    Health & human services. Watch at 2:19 Brox asphalt plant complaints · 2 meetings

    Health department staff and board members reported on a recent informational meeting with the Massachusetts Department of Environmental Protection, Marlborough Board of Health, Brox plant leadership, and local residents concerning persistent asphalt odor complaints. Brox recently installed a closed-loop system intended to cycle exhaust back into the burner, in addition to existing EcoSorb and mister systems, though Southborough residents continue to report odors. MassDEP reported that existing emissions testing meets federal standards and that current operations pose no known health hazard, but officials stressed that residents must submit detailed real-time logs to help identify operational patterns.

    • Brox installed a closed-loop burner exhaust system before Memorial Day weekend to mitigate odor
    • A similar mitigation system in Ipswich reportedly reduced resident complaints from 165 down to zero
    • MassDEP confirmed Brox operates within state and EPA permit standards and poses no known direct health threat
    • Residents are requested to log specific odor descriptors, intensity levels, durations, and symptoms directly to MassDEP

    Outcome: Discussion only; health staff will continue sharing state data and tracking resident reports

    Why it matters: Residents near the Marlborough border continue to report pervasive asphalt odors that affect quality of life, though state regulators report the plant remains compliant with environmental laws.

  • Enforcement order for Turnpike Road body art business

    Health & human services. Watch at 17:54 7 Turnpike Road bodywork compliance · 3 meetings

    Health department staff informed the board that a certified cease-and-desist letter mailed to an unlicensed body art business on Turnpike Road was returned as undeliverable. Staff recommended utilizing a town constable to personally serve the order. The business has repeatedly failed to apply for required establishment and practitioner licenses.

    • Business location is on Turnpike Road
    • Certified mailing returned undeliverable on the day of the meeting
    • Enforcement will proceed with in-person service by a constable

    Outcome: Staff directed to arrange service of the cease-and-desist notice through a constable

  • Body art regulations revisions

    Health & human services. Watch at 19:15 Board of Health body art regulations

    The board reviewed proposed modifications to the local body art regulations to align more closely with state model language and update local operating standards. Changes include restoring requirements for practitioner training in CPR, first aid, bloodborne pathogens, and anatomy, establishing clear standards for apprenticeships, and explicitly adding vaping to the list of prohibited activities in procedure areas.

    • Apprentices must meet training requirements before performing skin piercings
    • Section 6 Item 14 was updated to prohibit vaping alongside smoking, eating, and drinking in procedure areas
    • Clarified that Southborough regulations are enforceable rules rather than state guidance models

    Outcome: Approved unanimously with the vaping amendment

  • Public Health Director annual evaluation and compensation

    Staffing & operations. Watch at 22:46

    The board reviewed and approved the compiled annual performance evaluation for the public health director at the end of her second year in the combined regional role. The evaluation was strongly positive, highlighting team leadership and department management, and the board approved a 5% salary increase aligned with town Salary Administration Plan guidelines for FY27.

    • Director completed her second year managing the regionalized department
    • Board approved a 5 percent compensation increase for FY27 aligned with SAP personnel adjustments

    Outcome: Approved unanimously

  • Draft updates to septic and well regulations

    Health & human services. Watch at 25:09 Well and septic regulation amendments · 2 meetings

    Staff provided an update on drafting revisions to Southborough's local septic and private well regulations. The proposed updates incorporate minor adjustments to septic rules and more extensive updates to private well regulations based on established Northborough practices. The board will hold a public hearing on the proposed regulatory changes at an upcoming meeting.

    • Revisions will affect both local septic bylaws and private well regulations
    • Language will be circulated to board members with strike-throughs and highlighted changes
    • Changes require a formal public hearing before adoption

    Outcome: Public hearing to be scheduled for the next regular meeting

Routine business (2 items)
  • Sanitary inspector contract renewal

    Staffing & operations. Watch at 1:21

    After convening in executive session to discuss non-union contract negotiations, the board returned to open session to vote on the sanitary inspector agreement. The board approved the contract renewal for fiscal year 2027.

    • Contract renewal covers the town sanitary inspector for FY27
    • Executive session held under M.G.L. Chapter 30A Section 21(a)(2)

    Outcome: Approved unanimously

  • Routine business

    Governance & committees. Watch at 1:56

    The board conducted routine business, including approving meeting minutes from April 7, 2026, and May 5, 2026. Following annual town elections, the board also reorganized its officers, re-electing Chelsea Malinowski as chair, Safdar Medina as vice chair, and Elizabeth Zulick as secretary, and set its July meeting date.

    • Approved minutes of April 7, 2026 and May 5, 2026
    • Chelsea Malinowski re-elected Chair
    • Safdar Medina elected Vice Chair
    • Elizabeth Zulick elected Secretary
    • Next meeting scheduled for July 7, 2026 at 11:00 AM

    Outcome: Minutes approved; board officers elected unanimously

Votes

MotionResultTime
Approve the renewal of the sanitary inspector contract for FY27 Passed, 3-0 1:49
Approve the updated body art regulations with revisions including adding vaping to the operational prohibitions in Section 6 Passed, 3-0 22:36
Approve the performance review for the public health director and recommend a 5 percent pay increase aligned with Salary Administration Plan employees for FY27 Passed, 3-0 24:32
Elect Chelsea Malinowski as chair, Safdar Medina as vice chair, and Elizabeth Zulick as secretary for FY27 Passed, 3-0 28:47

Next steps and dates mentioned

  • July 7, 2026 at 11:00 AM: Board of Health meeting with scheduled public hearing on septic and well regulations

Community Preservation Committee

Thursday, June 11, 2026, 2 hr 3 min recording. Watch the full meeting · All Community Preservation Committee meetings

The Community Preservation Committee reviewed major Fall Town Meeting proposals, including an estimated $900,000 golf course irrigation overhaul and Fay Memorial Park upgrades.

Full summary 8 topics · public comment

The Community Preservation Committee held its annual public forum to review Community Preservation Act funding, historical town allocations, and the upcoming application cycle. The committee discussed several pending projects being prepared for the Fall Special Town Meeting, focusing heavily on a cost-engineered irrigation system for the Southborough Golf Course estimated at $900,000 and parking solutions for Fay Memorial Park. Members also reviewed standardized signage designs to recognize CPA-funded town projects and deferred voting on the updated application handbook to an upcoming meeting.

  • Annual CPA public forum and program overview

    Budget & taxes. Watch at 2:00

    The committee presented its annual overview of the Community Preservation Act in Southborough, covering governance, local surcharge revenues, state matches, and statutory funding allocations. Since adoption in 2003, the town has collected approximately $6.6 million locally with $2.5 million in state matches. Members outlined the minimum 10 percent statutory buckets for open space, historic preservation, and community housing, along with the September 15 application deadline for next spring's Annual Town Meeting.

    • Southborough voters adopted a 1 percent CPA property tax surcharge in 2003, with exemptions for qualifying seniors and low-income homeowners.
    • The surcharge costs the average single-family home assessed at $991,000 approximately $127.95 per year.
    • Total CPA funds collected to date exceed $9.1 million, including over $2.5 million from the state trust fund match.
    • Annual revenue is divided into open space (10 percent), historic preservation (10 percent), community housing (10 percent), administration (up to 5 percent), and budgeted reserve (65 percent).
    • The deadline for applications seeking funding at the 2027 Annual Town Meeting is September 15.

    Outcome: Information presented and discussed with attendees.

  • Fay Memorial Park improvements update

    Parks, trails & recreation. Watch at 49:40 Fayville Memorial Park improvements · 10 meetings

    The vice chair presented an update on the Recreation Commission's proposal to repurpose Fay Memorial Park to add a dog park and a children's splash pad. Parking remains the primary neighborhood concern, and the project engineer recently delivered a traffic and parking study outlining potential layout expansions and dedicated park spaces. The Recreation Commission intends to submit a revised application by June 30 for consideration at the Fall Special Town Meeting.

    • Proposed park enhancements include a dog park and splash pad.
    • A parking study completed with engineering consultant Activitas provides options to expand and protect parking spaces for park visitors.
    • The Recreation Commission will coordinate with the DPW and the Select Board regarding parking utilization and agreements near the Historical Society.
    • The committee reiterated that revised applications for the Fall Special Town Meeting must be submitted by June 30.

    Outcome: Discussion only; revised proposal expected by June 30.

    Why it matters: The project would introduce a new dog park and water recreation amenity in town while addressing ongoing parking and traffic concerns for adjacent residents.

  • Rural Cemetery stone water tower restoration

    Parks, trails & recreation. Watch at 54:40 Rural Cemetery stone water tower restoration · 3 meetings

    The Historical Commission representative provided an update on the proposed restoration of the historic stone water tower in the Rural Cemetery. Discussions remain largely stalled due to pending structural and cost consultant evaluations, as well as jurisdiction and coordination issues with the Rural Cemetery Committee. Proponents may withdraw the application from the fall warrant if alternative non-CPA solutions or independent plans proceed.

    • The project seeks to restore the historic stone water tower located inside the Rural Cemetery.
    • A consultant conducted an initial inspection and rough estimate, but a full cost report has not been completed.
    • Overlapping jurisdiction between the Historical Commission and the Cemetery Committee has delayed finalizing a CPA scope.
    • The application may be formally withdrawn if a viable submission cannot be completed.

    Outcome: Update received; project status remains pending.

  • Southborough Golf Course irrigation replacement

    Parks, trails & recreation. Watch at 56:22 Southborough Golf Club irrigation replacement · 16 meetings

    The DPW superintendent and Golf Course Committee members discussed a revised funding plan for the golf course irrigation system after initial construction bids substantially exceeded available funds. Value engineering identified approximately $160,000 in scope reductions, but engineers determined a necessary booster pump station will add roughly $200,000, bringing total project estimates to about $900,000. Proponents are reviewing how much to contribute from the golf course revolving fund, which has about $200,000 available but faces a statutory annual spending limit of $75,000 without Select Board and Advisory Committee approval.

    • Original construction bids came in well over the appropriated budget, triggering value engineering efforts.
    • Proposed cost reductions shaved roughly $160,000, but a newly required booster pump station adds approximately $200,000.
    • Preliminary revised total cost estimate for the irrigation project is approximately $900,000.
    • The golf course revolving fund has approximately $200,985 in uncommitted funds, but town policy caps annual revolving expenditures at $75,000 unless joint approval is granted.
    • The DPW and Golf Course Committee plan to submit a revised application and schedule by June 30, with the option to postpone to Spring Town Meeting if loose ends remain.

    Outcome: Discussion only; revised application package due by June 30.

    Why it matters: Replacing the failing irrigation system requires significant capital funding, potentially drawing hundreds of thousands of dollars from CPA reserves and municipal revolving funds.

  • Standardized CPA recognition signage

    Governance & committees. Watch at 1:24:05

    The committee reviewed efforts to install permanent signs acknowledging CPA funding at completed projects across town. Members examined sample PVC and bronze sign mockups for the library facade, the library interior local history collection, and the golf course. Discussion centered on specific wording choices, including whether to credit 'residents', 'citizens', or 'taxpayers', and selecting standard dimensions to maintain consistency while avoiding sign clutter.

    • Samples presented included 12-by-16 inch PVC signs estimated at $100 each and larger versions at $150 each from Signarama.
    • Cast bronze signs for prominent historic structures like the library exterior and water tower range from $500 to $1,500.
    • The Library Trustees favored crediting the 'residents' of Southborough, while public comment urged using 'taxpayers'.
    • Sign mounting locations will be tailored per site, using fence mounts, posts, or building facades.

    Outcome: Wording and final sizes will be voted on at the next meeting.

Routine business (3 items)
  • Peninsula Trail project update

    Parks, trails & recreation. Watch at 1:22:48 Peninsula Trail Phase 2 · 22 meetings

    The committee briefly addressed the Peninsula Trail project application. Discussion was deferred until the applicant and committee members can coordinate following a previously canceled meeting.

    • Project proponents will be invited to discuss the proposal at an upcoming committee meeting.

    Outcome: Discussion continued to the next meeting.

  • FY27 application and handbook revisions

    Governance & committees. Watch at 1:55:18

    Members discussed updating the annual CPA application form and informational handbook. The committee agreed to provide editable Word document versions in addition to PDFs to avoid past issues with fillable forms, and agreed to review text changes and updated deadlines at the next meeting.

    • The committee will provide application forms in Microsoft Word format to simplify applicant submissions.
    • Updated dates and application instructions will be reviewed and finalized at the next session.

    Outcome: Handbook review deferred to the next meeting.

  • Routine business

    Governance & committees. Watch at 1:58:20

    The committee approved past meeting minutes and discussed scheduling its next meeting before the end of June. The meeting was adjourned at approximately 9:09 p.m.

    • Approved meeting minutes from February 26, 2026 and May 20, 2026.
    • Members agreed to poll dates for the next meeting prior to June 30.

    Outcome: Minutes approved; next meeting date to be scheduled via poll.

Public comment

  • The chair of the Master Plan Implementation Committee, speaking as a resident, asked how the Community Preservation Committee could collaborate to proactively advance priorities and recommendations identified in the town master plan. 24:17
  • A resident of 1 Chestnut Hill Road inquired about the requirements, historic restrictions, and Massachusetts anti-aid amendment rules governing CPA funding for private historic structures. 41:33
  • A resident of Woodbury Road recommended using the word 'taxpayers' rather than 'citizens' or 'residents' on CPA signs, noting that many property and business taxpayers contributing to the fund are non-residents. 1:30:54

Next steps and dates mentioned

  • June 30, 2026: Deadline for revised applications for Fall Special Town Meeting articles
  • Late June 2026: Next Community Preservation Committee meeting to finalize fall applications and sign wording
  • September 15, 2026: Application deadline for funding consideration at 2027 Annual Town Meeting

Zoning Board of Appeals

Wednesday, June 10, 2026, 1 hr 9 min recording. Watch the full meeting · All Zoning Board of Appeals meetings

The Zoning Board granted side setback relief for 34 Turnpike Road conditioned on Board of Health septic approval.

Full summary 4 topics · 3 votes · public comment

The Southborough Zoning Board of Appeals met to address multiple property applications and zoning revisions. The board approved an applicant request to withdraw an application for 22 Newton Street without prejudice. Members also debated draft updates to the town two-family zoning bylaw to remove a two-year residency waiting period and refine dimensional requirements. Finally, the board approved a 1.3-foot side setback relief for 34 Turnpike Road after addressing septic proximity concerns and abutter objections regarding bedroom count and Title 5 compliance.

  • 22 Newton Street withdrawal request

    Zoning & development. Watch at 0:20 22 Newton Street garage variance · 2 meetings

    The applicant for 22 Newton Street requested to withdraw their application without prejudice. The proposal previously involved constructing a two-car garage that blocked access to the backyard. The board voted to grant the withdrawal without prejudice so the homeowner can reconsider options.

    • Address: 22 Newton Street
    • Prior proposal involved constructing a two-car garage
    • Applicant requested withdrawal without prejudice

    Outcome: Application withdrawn without prejudice

  • Two-family zoning bylaw update discussion

    Zoning & development. Watch at 2:30 Two-family dwelling zoning amendment · 11 meetings

    Board members reviewed draft revisions to the two-family zoning bylaw stemming from recent updates to accessory dwelling unit bylaws. Discussion focused on eliminating the requirement that a homeowner must reside in a newly constructed home for two years before converting it into a two-family dwelling. Members also discussed curb cut limitations, lot size rules, and harmonizing definitions with the Planning Board ahead of fall Town Meeting.

    • Bylaw currently requires a two-year wait before adding a second unit in newly constructed homes
    • Current regulations require a minimum lot size of 15,000 square feet for two-family dwellings
    • Board plans to coordinate revised draft language with the Planning Board in July

    Outcome: Discussion held; staff and board members will refine draft language for the July 15 meeting

  • 34 Turnpike Road setback relief and as-built modification

    Zoning & development. Watch at 16:15 34 Turnpike Road special permit · 2 meetings

    The board resumed a public hearing on an addition at 34 Turnpike Road where as-built construction deviated from permitted plans. To resolve an unauthorized foundation bump-out encroaching on septic system setbacks, the contractor proposed cutting back the foundation at grade, filling the void with flowable fill, and supporting the upper floor with an interior steel beam. The applicant also requested dimensional relief for the side setback, which measured 13.9 feet instead of the required 15 feet. After hearing abutter objections concerning overall house size and septic capacity, the board approved the 1.3-foot setback relief on the condition that the Board of Health reviews and certifies the septic capacity.

    • Address: 34 Turnpike Road
    • Foundation bump-out of approximately 5 by 10 feet encroached on septic system setbacks and must be removed at grade
    • Requested side setback relief for an as-built distance of 13.9 feet versus the required 15 feet (a 1.3-foot encroachment)
    • Approval is conditioned on explicit Board of Health confirmation that the septic capacity meets the dwelling bedroom count
    • Town planner noted a written decision will be filed within two weeks, initiating a 20-day appeal period

    Outcome: Relief approved with conditions

    Why it matters: The decision resolves a zoning non-conformity on an expanded home while ensuring the septic system is verified by health officials to protect neighborhood ground conditions.

Routine business (1 item)
  • Routine business

    Governance & committees. Watch at 1:47

    The board reviewed and approved the draft meeting minutes from its previous meeting on May 6.

    • Approved minutes of the May 6 meeting with minor amendments

    Outcome: Minutes approved

Votes

MotionResultTime
Withdraw the application for 22 Newton Street without prejudice Passed, 5-0 1:15
Close the public hearing for 34 Turnpike Road Passed, 5-0 54:26
Approve the request for 1.3 feet of side setback relief for 34 Turnpike Road subject to review and approval by the Board of Health confirming septic system capacity meets the bedroom count Passed, 5-0 1:04:20

Public comment

  • A representative for the abutting property owner at 32 Turnpike Road objected to the expansion of 34 Turnpike Road, stating the lot historically housed a 750-square-foot dwelling with zero road frontage and argued that the current structure amounts to an unpermitted four-bedroom house. He urged the board to postpone granting zoning relief until the Board of Health formally reviews the septic system under Title 5. 31:24

Next steps and dates mentioned

  • July 15, 2026: Next Zoning Board of Appeals meeting featuring three new hearings, including two variances and one special permit for Costco lighting and retaining walls
  • August 12, 2026: Zoning Board of Appeals meeting
  • September 16, 2026: Zoning Board of Appeals meeting

Library Board of Trustees

Monday, June 8, 2026, 1 hr 13 min recording. Watch the full meeting · All Library Board of Trustees meetings

The Library Trustees elected new board leadership, clarified parking lot repaving procedures with the DPW, and welcomed a prospective trustee candidate.

Full summary 8 topics · 3 votes

The Library Board of Trustees elected a new chair and vice chair following the resignation of the former chair, discussing potential term rotation practices. Public Works Department Director Bill Cundiff joined the board to clarify that repaving the library parking lot must proceed as a capital project request initiated by the trustees rather than DPW operations. Trustees also reviewed proposed Community Preservation Committee signage wording, authorized the use of trust funds for year-end book materials, and scheduled a joint meeting with the Select Board to appoint candidate Molly Schofield to the vacant trustee seat.

  • Director's and expense reports

    Library, arts & community. Watch at 1:52

    The library director provided updates on year-end budget closeout, facility repairs, and technology upgrades. All public computers and the fax machine have been replaced, and plans are moving forward to safely remove a disruptive bird nest before upcoming concrete repairs. The director and trustees also discussed options and estimated costs for repairing antique clocks in the Judy Williams reading room.

    • Public computers and fax machine hardware upgrades were completed.
    • Concrete work near the entrance is being coordinated alongside a project at the Senior Center.
    • The library is contacting a clock museum in Grafton for estimates on repairing the entryway and grandfather clocks.
    • End-of-year funds may be directed toward high-demand digital audiobooks and e-books on Libby.

    Outcome: Reports accepted with no formal vote required.

  • Election of board officers

    Governance & committees. Watch at 14:40

    Trustees debated whether the board should adopt an informal practice of rotating the chair role every one to two years, noting other town boards rotate regularly. Following the discussion, the board formally nominated and elected new officers to fill the leadership vacancy.

    • A member suggested rotating the chair role every two years to share leadership responsibility.
    • Trustee Jane Davis was nominated and elected as board chair.
    • Trustee Amy Yazdani was nominated and elected as vice chair.

    Outcome: Jane Davis elected chair and Amy Yazdani elected vice chair by unanimous roll call votes.

  • DPW communication and library parking lot

    Buildings & facilities. Watch at 27:06 Library parking lot repaving · 3 meetings

    The board discussed a communication letter drafted to the Department of Public Works regarding maintenance delays and the library parking lot. DPW Director Bill Cundiff joined the discussion to explain that full parking lot repaving is a capital project that requires a town meeting warrant article sponsored by the trustees rather than a DPW operational repair. Cundiff offered to assist the library with engineering contacts and project scoping to bring a capital request to Town Meeting.

    • DPW Director Bill Cundiff explained DPW staffing shortages and heavy focus on road reconstruction projects.
    • Parking lot repaving must be brought as a trustee-sponsored capital request to Town Meeting.
    • Cundiff provided engineer names, survey drawings, and CAD files to assist with project planning.
    • Board members agreed to meet and coordinate future maintenance communications directly with the DPW director.

    Outcome: Trustee leadership agreed to review correspondence and coordinate directly with DPW on capital scoping.

    Why it matters: Clarifies the funding and project management pathway required to repair the library parking lot at Town Meeting.

  • Library director annual evaluation

    Staffing & operations. Watch at 57:06

    Trustees reviewed the final written evaluation document for Library Director Ryan Donovan. The board agreed to strike a line from the document regarding parking lot research before the chair signs the final certification form.

    • Trustees agreed to delete a sentence stating trustees agree the director does not need to research parking lot issues.
    • The chair will meet with the director offline to sign the town evaluation certification form.

    Outcome: Evaluation adjusted to strike the parking lot sentence; signing scheduled offline.

  • Authorization of Mary Finn Fund

    Library, arts & community. Watch at 1:00:18

    The director requested standing authorization to utilize the town-managed Mary Finn Fund trust to cover book expenses if end-of-year collection invoices exceed the operating budget line item. The trust was established by a family bequest with the explicit stipulation that funds be spent on books.

    • The Mary Finn Fund is a town-managed trust fund restricted to purchasing books.
    • Authorization allows invoices received late in the fiscal year to be paid from the trust without exceeding the municipal operating budget.

    Outcome: Approved 5-0.

    Why it matters: Enables the library to cover fiscal year-end book purchasing overages using dedicated private bequest funds rather than general tax appropriations.

  • Prospective trustee appointment

    Governance & committees. Watch at 1:01:42

    Resident Molly Schofield was introduced as an applicant to fill the vacant seat on the Board of Trustees through the next annual town election. Trustees reviewed the appointment procedure, which requires a joint meeting and vote with the Select Board.

    • Molly Schofield applied for the vacancy created by Marguerite Landry's resignation.
    • A joint meeting with the Select Board is scheduled for June 16, 2024, around 6:45 PM to vote on the appointment.
    • The appointee will serve until the spring 2025 town election, where the remainder of the term will be on the ballot.

    Outcome: Trustees agreed to attend the June 16 joint meeting with the Select Board.

Routine business (2 items)
  • Routine business

    Governance & committees. Watch at 0:15

    The board approved the minutes from the May 11 meeting and adjourned the session.

    • Minutes of May 11 were approved unanimously.
    • Next regular board meeting scheduled for July 13, 2024 at 11:00 AM.

    Outcome: Meeting adjourned at 12:16 PM.

  • Community Preservation Committee signage language

    Library, arts & community. Watch at 46:15

    The director presented proposed wording from the Community Preservation Committee for signs acknowledging CPA funding for facade restoration and archival preservation. Trustees evaluated proposed phrasing and unanimously preferred acknowledging 'residents' rather than 'citizens.'

    • Signs will acknowledge CPA funding for the facade restoration and the Southborough Library Local History Collection.
    • Trustees unanimously directed staff to ensure the text reads 'residents' instead of 'citizens'.
    • Trustees corrected the collection title from 'Material Archive' to 'Local History Collection'.
    • Proposed sign dimensions discussed were roughly 12 inches by 18 inches.

    Outcome: The director will convey the board's wording preferences to the Community Preservation Committee.

Votes

MotionResultTime
Elect Jane Davis as Chair of the Library Board of Trustees Passed, 5-0 25:27
Elect Amy Yazdani as Vice Chair of the Library Board of Trustees Passed, 5-0 26:03
Authorize the use of the Mary Finn Fund to cover book materials if needed for fiscal year-end overages Passed, 5-0 1:01:25

Next steps and dates mentioned

  • June 16, 2024 at 6:45 PM: Joint meeting with the Select Board to appoint a trustee to fill the board vacancy
  • July 13, 2024 at 11:00 AM: Next regular Library Board of Trustees meeting

Other meetings

Tricentennial Committee

Wednesday, June 10, 2026, 1 hr 42 min recording. Watch the full meeting · All Tricentennial Committee meetings

The Southborough Tricentennial Committee approved up to $25,000 for the Firemen's Muster and reviewed plans for banners, tours, and anniversary events.

Full summary 8 topics · 1 vote

The committee advanced planning across several 2027 anniversary events and community projects. Members voted to cap the Firemen's Muster budget at $25,000 and discussed banner sizing and hardware for village poles with an estimated cost of $3,500 to $5,000. Updates were also provided on school tours, a town coloring book, historic house tours, drone show contracts, time capsule coordination with local scouts, and commemorative tree donations.

  • Town banners and pole brackets

    Roads, water & infrastructure. Watch at 0:57 Tricentennial commemorative street banners · 9 meetings

    Members reviewed pole measurements and photos from neighboring towns to establish banner specifications for Southborough's villages. The committee settled on 18-by-36-inch banners with stainless steel screw clamp brackets to avoid damaging utility poles. With estimated costs of around $70 per set, the total estimated cost for 40 to 50 banners is $3,500 to $5,000.

    • Banner dimensions set at 18 inches wide by 36 inches high.
    • Estimated budget range between $3,500 and $5,000 for approximately 40 to 50 banners.
    • Banners will be placed in Fayville, Cordaville, Southville, and Main Street.
    • Final design options will be presented in July for manufacturing before September.

    Outcome: Committee agreed on banner dimensions and a $3,500 to $5,000 budget target.

  • History in Bloom, school tours, and family events

    Library, arts & community. Watch at 21:42

    The committee reviewed progress on educational and youth events. The Southborough Garden Club confirmed dates for 'History in Bloom' for April 15-17, 2027. St. Mark's School faculty is developing a tour script and identifying historical artifacts for public display, and local historian Nick Noble drafted a town history coloring book for children ages 5 to 8.

    • History in Bloom scheduled for April 15-17, 2027.
    • St. Mark's School working script will be written over the summer for student-led tours.
    • Children's coloring book printing estimated at a few hundred dollars for distribution at Fay School and potentially schools and libraries.

    Outcome: Planning ongoing over the summer.

  • Oral history, graveyard tour, and house tour updates

    Library, arts & community. Watch at 30:02

    Volunteers are collecting oral history interviews from current and former residents, with formatting and historical photo matching underway. A committee member is coordinating with the Nipmuc tribe regarding sensitive historical sites for the graveyard tour. Work is also advancing on draft homeowner and ticket holder agreements for the historic house tour.

    • Oral history project continues to record interviews and source photographs.
    • Coordination underway with the Nipmuc tribe regarding graveyard tour sites.
    • House tour participant agreements are being prepared for Town Counsel review.

    Outcome: Draft contracts being finalized for legal review.

  • Parade planning and drone show contract

    Library, arts & community. Watch at 40:34 First Day 2027 celebration · 7 meetings

    The committee reviewed a three-page draft of participation rules and standards for the anniversary parade, covering safety, breakdowns, and animal waste management. Members also discussed a pending contract for a drone light show and noted the need to confirm whether municipal procurement bidding rules apply.

    • Parade standards and participant contracts will be distributed to prospective entrants.
    • Town Administrator must execute formal municipal event contracts.
    • Drone show contract is currently being reviewed for legal language and procurement requirements.

    Outcome: Committee will circulate the parade contract to participants and check procurement rules on the drone show.

  • Firemen's Muster budget and sponsorship standards

    Library, arts & community. Watch at 45:58 2027 Tricentennial Firefighter's Muster · 4 meetings

    The committee voted to approve an initial budget cap of up to $25,000 for the Firemen's Muster event. Discussion centered on the return of Southborough's historic first fire engine, the Falcon, to the fire club's museum, and securing commitments from two live bands. Members also debated the boundary between town tricentennial branding, corporate event sponsorships, and club fundraising.

    • Voted 6-0 to approve a muster budget not to exceed $25,000 at this time.
    • The historic 'Falcon' hand tub fire engine has been returned to the Southborough club for restoration.
    • Two musical acts have committed to perform for up to four hours, with staging arrangements pending.
    • Guidelines will be established regarding how corporate sponsors and 501(c)(3) funds are recognized on promotional materials.

    Outcome: Budget approved up to $25,000.

    Why it matters: Commits up to $25,000 in anniversary celebration funding for the town-wide muster event and establishes promotional rules.

  • Time capsule and youth organization outreach

    Library, arts & community. Watch at 1:01:40 Tricentennial time capsule · 5 meetings

    Committee member Eric updated the group on plans for a 50-year time capsule to be sealed during the tricentennial. Organizers are creating intake guidelines and preservation standards for community submissions and plan to partner with local Boy Scout troops to help manage and inventory items.

    • Time capsule designed to preserve community items for 50 years.
    • Outreach underway to local Boy Scout troops (Troop 1 and Troop 92) to assist with logistics.

    Outcome: Outreach to scout leaders to continue over the summer.

  • Glow SoBo, legacy trees, and brick fundraiser

    Library, arts & community. Watch at 1:08:58 Glow SoBo holiday lighting · 4 meetings

    The Glow SoBo working group is evaluating decorative uplighting for the Town House and the Southborough Library with a landscape lighting contractor. For the legacy tree project, a local supplier offered to donate trees to be planted in each of the four villages in fall 2026 or spring 2027 in consultation with the Tree Warden and DPW. Meanwhile, roughly 100 commemorative bricks have been sold toward a 300-brick fundraising goal.

    • Landscape company will assess exterior lighting for the Library and Town House.
    • Tree donations offered for all four villages; sites and species to be coordinated with the Tree Warden and DPW.
    • Approximately 100 commemorative bricks sold to date toward a 300-brick target.
    • The committee is seeking two additional members to fill vacancies on the nine-member board.

    Outcome: Site visits and outreach will proceed through the summer.

Routine business (1 item)
  • Routine business

    Governance & committees. Watch at 0:15

    The committee approved the meeting minutes from May 13, 2026, and later adjourned the meeting.

    • Minutes of May 13, 2026, approved unanimously.

    Outcome: Approved

Votes

MotionResultTime
Approve a budget not to exceed $25,000 at this time for the Firemen's Muster based on the event outline. Passed, 6-0 48:56

Next steps and dates mentioned

  • June 13, 2026: Tricentennial informational table at the Pilgrim Church chicken barbecue
  • June 16, 2026: Periodic committee update to the Select Board
  • July 15, 2026: Next Tricentennial Committee meeting

Trails Committee

Thursday, June 11, 2026, 1 hr 12 min recording. Watch the full meeting · All Trails Committee meetings

The Trails Committee finalized preparations for an upcoming Peninsula Trail work party and prepared its Phase 2 CPA funding application.

Full summary 7 topics

The Southborough Trails Committee met virtually to plan trail blazing and wayfinding for the Peninsula Trail along Massachusetts Water Resources Authority property. The committee also coordinated logistics for an upcoming trail building work party off Boston Road, including volunteer safety, tool prep, and parking arrangements with Sanofi. Additionally, members discussed updates to their Community Preservation Act application for Phase 2 bridge construction ahead of the June 30 deadline and evaluated purchasing promotional event banners.

  • Peninsula Trail signage and wayfinding

    Parks, trails & recreation. Watch at 19:00 Peninsula Trail Phase 2 · 22 meetings

    The committee evaluated signage and trail markers needed along the Peninsula Trail and its overlap with the Boroughs Loop and Aqueduct trails. Because much of the corridor follows an open MWRA access road without nearby trees, members discussed how to mark routes without cluttering the path or obstructing maintenance mowers.

    • Identified the need for an entry welcome sign near the ADA parking area off Boston Road.
    • Discussed installing low quarter-mile marker posts similar to cross-country running trail markers.
    • Noted the need for directional arrows where trails diverge from MWRA restricted service areas.
    • Considered utilizing existing metal fence posts and aluminum signs to avoid digging unnecessary post holes.

    Outcome: Committee agreed to field-assess sign locations during the upcoming work party before purchasing additional posts.

  • Trail work party logistics and safety

    Parks, trails & recreation. Watch at 45:00 Peninsula Trail Phase 2 · 22 meetings

    Members finalized logistics for an upcoming trail maintenance work party scheduled for Saturday morning. Volunteer work will focus on building out a new section of natural surface trail and clearing brush and poison ivy from two older segments.

    • Work party scheduled for Saturday, June 13, starting at 8:00 AM.
    • Sanofi granted permission for volunteer vehicle parking along Route 30.
    • Amber Stearns, trail coordinator for AMC and the Bay Circuit Trail, will attend to supervise trail building.
    • Volunteers will be supplied with Tyvek suits and washing stations due to prevalent poison ivy along parts of the trail.

    Outcome: Logistics finalized for the Saturday work session.

  • Peninsula Trail Phase 2 CPA funding application

    Parks, trails & recreation. Watch at 56:36 Peninsula Trail Phase 2 · 22 meetings

    The chair gave an update on the upcoming Community Preservation Act application deadline for Phase 2 of the Peninsula Trail project. The committee is working to secure updated engineering quotes and stakeholder letters of support for the proposed bridge and boardwalk.

    • Application is due June 30, 2026.
    • Seeking an updated scope and quote from engineering firm Beals and Thomas for bid preparation and construction oversight.
    • Collecting updated letters of support from town boards and state entities.
    • Exploring wood decking instead of composite decking on the prefabricated bridge structure to contain costs.

    Outcome: Chair will continue compiling application materials ahead of a June 25 review meeting.

Routine business (4 items)
  • Yoga on the Trails program review

    Parks, trails & recreation. Watch at 7:20

    The committee reviewed the recent kickoff of the Yoga on the Trails program held the previous weekend. Approximately 20 participants attended the outdoor session led by the instructor. Members noted the event was successful and discussed minor adjustments to future event registration confirmations.

    • Around 20 participants attended the inaugural session.
    • National Grid work mats in the area did not disrupt the event.
    • The next scheduled session is in July.

    Outcome: Discussion only; program will continue as scheduled.

  • Routine business

    Governance & committees. Watch at 10:00

    The committee reviewed and approved meeting minutes from earlier sessions. Members noted updates regarding boardwalk materials and minor administrative adjustments.

    • Reviewed minutes from January 27, 2026, and June 1, 2026.
    • Added standardized disclaimer note regarding documents shared during meetings.

    Outcome: Minutes of January 27, 2026, and June 1, 2026, approved as amended.

  • Town Tercentennial celebration participation

    Library, arts & community. Watch at 58:15

    The committee discussed an invitation from Southborough's Tercentennial Committee to participate in town celebration activities planned for next year. Members supported the idea of hosting a trail walk or historical hike highlighting town paths.

    • Celebration marks Southborough's 300th anniversary in 2027.
    • Proposed activities include a Trail Awareness Day or guided historical trail walk.

    Outcome: Committee indicated interest in participating and will coordinate with the Tercentennial Committee as planning advances.

  • Committee event banner flag purchase

    Parks, trails & recreation. Watch at 1:00:50

    Members discussed purchasing a portable promotional feather or teardrop banner flag using remaining funds from the current fiscal year budget. The banner will be displayed at town events such as Heritage Day, volunteer trail workdays, and Yoga on the Trails.

    • Targeting a 10-foot tall double-sided flag with a collapsible folding X-base for easy transport.
    • Flag will feature the Southborough Trails Committee logo in official committee colors.
    • Committee opted against specific event taglines so the flag can be reused across different programs.

    Outcome: Chair will research vendor options and prices for a double-sided flag and folding base.

Next steps and dates mentioned

  • June 13, 2026, at 8:00 AM: Trail construction and maintenance work party off Boston Road
  • June 25, 2026, at 6:30 PM: Next Trails Committee meeting
  • June 30, 2026: Deadline for Community Preservation Act Phase 2 grant application